County will replace third bridge along Ferguson Road

Jefferson County Commissioners on Monday approved a contract to begin design work on a bridge replacement on Ferguson Road between K-16 Hwy. and K-92 Hwy.

The project is expected to begin sometime this spring and construction is expected to last about 60 days.

This is the third and final bridge scheduled for a replacement along Ferguson Road. Two bridges south of K-92 on Ferguson Road have been replaced this year.